Margin tracking software for subcontractors
Last updated 2026-11-10 · 5 min read
Margin tracking software for a subcontractor has to hold five things for each job: the priced budget, the costs committed by orders, the costs received but not yet invoiced, the costs invoiced, and the value earned. Accounts software holds some of these, estimating and purchasing tools hold others. Choose a set-up that brings them together, job by job, every month.
Most subcontractors find out a job's real margin at the end. Software can help you see it sooner, but only if it has the right numbers in it. This page is about what those numbers are and which tools hold them. The method itself, from baseline to weekly review, is in the guide to tracking margin on a live interiors job.
Which numbers does margin tracking need?
| Number | Where it comes from | Where it often lives |
|---|---|---|
| Budget | The winning price, by cost line | Estimate or costed BoQ |
| Committed cost | Orders placed but not yet delivered | Purchasing records or a call-off register |
| Received, not invoiced | Signed deliveries with no invoice yet | Goods received notes or delivery notes |
| Invoiced cost | Checked supplier and labour invoices | Accounts software |
| Labour cost | Timesheets, payroll and labour-only invoices | Payroll and accounts |
| Value earned | Valuations and agreed variations | Valuations, often a spreadsheet |
If these live in five places, a margin figure needs someone to pull them together by hand each month. That is what a CVR does on paper. Software helps when fewer of the numbers have to be copied across.
Why can accounts alone give the wrong margin?
Accounts software sees invoices. A job's cost runs ahead of its invoices, because materials arrive and labour works before the bills come in.
For illustration only, with assumed figures: a £100,000 job was priced at a 15% margin. At month four, £50,000 has been valued for work done.
| Accounts view | Full view | |
|---|---|---|
| Value to date | £50,000 | £50,000 |
| Invoiced costs | £36,000 | £36,000 |
| Delivered and signed for, not yet invoiced | not shown | £4,000 |
| Labour worked, not yet in the accounts | not shown | £3,000 |
| Cost to date | £36,000 | £43,000 |
| Margin to date | 28% | 14% |
The accounts suggest the job is running well ahead of its tender margin. The full view says it is slightly behind. Count each delivery once: from its goods received note until the invoice arrives, then from the invoice instead. Never add both, or the cost is doubled.
What types of tool are there?
- Accounts software is the record of what was invoiced and paid. It is accurate about the past, but usually cannot see deliveries without invoices or orders not yet delivered.
- Spreadsheets can hold everything, built as a CVR or cost report. They depend on someone gathering the numbers each month.
- Construction management or job costing systems can bring budgets, commitments and costs together. Check how much setup they need and whether they suit a subcontractor's scale.
- Trade-specific tools may link the priced job to orders and deliveries closely. Check which of the numbers above they hold and which still come from elsewhere.
No type is right for every firm. Many subcontractors end up with two: one tool that follows the job from price to checked invoice, and the accounts.
What should you ask before you choose?
- Does it start from the budget you priced, by the same cost lines?
- Can it show committed and received costs, not only invoiced ones?
- How does it stop a delivery being counted twice when the invoice arrives?
- Where do labour costs come from, and how current are they?
- Can it hold valuations and variations, or do they stay in a spreadsheet?
- Can a director see every job on one page? The profit per job report shows what that page should hold.
- Can you export the figures if you change tools?
Test it on a job you know. If its margin at a past month end does not agree with what you now know was true, find out why before you rely on it.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above, and variations are on the Growth plan. Check which of the numbers above any tool holds, ours included, before relying on it for a margin figure. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can I track job margin in my accounts software?
Partly. It shows invoiced costs well, but usually misses deliveries and labour not yet invoiced, so the margin can look better than it is.
What is committed cost?
Cost you have agreed to by placing an order, before the goods arrive or the invoice comes in.
How often should margin be updated?
At least monthly, in line with your valuations. Many subcontractors also check costs weekly on larger jobs.
Does margin tracking software replace a CVR?
It can supply most of the numbers, but someone still needs to review the value and cost and judge the forecast.