Job costing for subcontractors: the basics
Last updated 2026-11-10 · 6 min read
Job costing means recording every cost against the job that caused it, under a cost code that matches how you priced it. For a subcontractor, that means a job number on every order, invoice and timesheet, costs split by materials, labour, plant and job costs, and anything no single job caused kept as overheads. Without it, job margins are guesses.
Most small subcontractors know their profit for the year from the accounts. Far fewer know which jobs made it and which lost it. Job costing answers that, and every other job report depends on it.
What counts as a job cost?
A cost belongs to a job if you would not have had it without that job:
- Materials ordered and delivered for it
- Labour of your own operatives while they work on it, at their full cost
- Payments to labour-only gangs and other subcontractors for it
- Supervision time spent on it
- Plant, access and hire for it
- Skips, distribution, travel and parking for it
Office staff, the yard, insurance, vehicles not dedicated to one site, accountancy and your own time running the business are overheads. They are real costs, but they are recovered across jobs, not coded to one.
What cost codes should you use?
Use codes that match the lines of your tender build-up, so that you can compare like with like later. Keep the list short enough that site staff and office staff use it the same way. A starting list to adapt:
| Code | Group | What goes there | Source document |
|---|---|---|---|
| 100 | Boards | Plasterboard of every type | Invoice, checked against delivery |
| 110 | Metal | Studs, tracks, channels, angles | Invoice, checked against delivery |
| 120 | Insulation | Insulation in partitions and linings | Invoice, checked against delivery |
| 130 | Fixings and finishing | Screws, tape, filler, beads, sealant | Invoice, checked against delivery |
| 200 | Own labour | Operatives' hours at full cost per hour | Timesheet, by job and activity |
| 210 | Labour-only gangs | Gang payments | Measure sheet or gang invoice |
| 220 | Supervision | Supervisor and site manager time | Timesheet |
| 300 | Plant and access | Towers, platforms, hire and transport | Hire invoice and off-hire note |
| 400 | Job costs | Skips, distribution, travel, parking | Invoice or expense claim |
| 5xx | Variations | One code per variation, by number | Variation log |
Giving each variation its own code keeps its cost out of the original scope, so you can see whether the base job made money.
How do you split a mixed invoice?
Merchant invoices often cover several jobs, and some stock for the van. Split each invoice line by the job number on the order.
For illustration only, with assumed figures. A merchant invoice comes to £4,860 before VAT.
| Invoice lines | Job | Code | Amount |
|---|---|---|---|
| Boards | 2417 | 100 | £3,200 |
| Studs and track | 2417 | 110 | £1,100 |
| Screws and tape | 2420 | 130 | £410 |
| Van stock and consumables | Overheads | Not a job | £150 |
| Total before VAT | £4,860 |
Check each line against the order and the delivery note before you code it. The guide to checking supplier invoices covers that step. An unchecked invoice coded to a job puts someone else's mistake into your job cost.
How do you cost labour to a job?
From timesheets that record the job and the activity, not only the hours. An operative who spends three days on one job and two on another should appear on both, in the right proportion.
Charge the hours at your full cost per hour, including employer's on-costs, holiday, travel and tools, not just the hourly wage. The guide to setting your drylining labour rate shows how to work that figure out. Using wages only makes every job look better than it is.
What about costs that have not been invoiced yet?
At the end of each month, list what the job has used but not yet been billed for: goods received without an invoice, labour worked but not yet paid, hire still running. These are accruals. Add them to the job cost for that month, then reverse them when the invoices arrive. Without them, a job looks cheap in the month materials arrive and expensive in the month the invoice does.
How do VAT and CIS fit in?
If you are VAT registered and can reclaim the VAT you pay, record job costs net of VAT. CIS deducted from what you are paid is generally an advance payment towards your tax, not a cost of the job. Ask your accountant how both should be treated in your own records, and check HMRC's guidance on gov.uk.
What do you do with the job cost?
Once every cost carries a job and a code, you can compare each line with what you priced. The budget vs actual template is the next step, and it only works if the costing underneath is complete.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
How many cost codes does a subcontractor need?
Enough to match the main lines of your tender, and few enough that people use them properly. Ten to fifteen is plenty for most drylining jobs.
Should overheads be coded to jobs?
No. Keep them separate and recover them through your prices. Coding them to jobs hides where each job's direct costs went.
What if an invoice has no job number?
Ask the merchant to quote your order number on every invoice, and put the job number on every order. Query any line you cannot place.
Do small jobs need job costing?
Yes, even if it is just a job number on each cost. Small jobs are often where return visits and extra trips go unnoticed.