Drylining vs plastering
Last updated 2026-11-10 · 5 min read
Drylining fixes plasterboard to a frame or bonds it to the wall, then finishes the joints or skims the board. Plastering, in the traditional sense, applies wet backing and finish coats straight onto masonry. Drylining brings far less water into the building, so decoration can usually follow sooner. The specification normally decides which you price.
For a subcontractor the question is rarely which method is better in general. It is which one the job calls for, who is doing which part, and what that does to the programme and the price.
What is the difference between drylining and plastering?
| Drylining | Wet plastering | |
|---|---|---|
| What goes on the wall | Plasterboard on a metal or timber frame, or bonded with adhesive | Backing coat and finish coat of plaster, or a one-coat plaster |
| Background | Frame, or masonry for bonded board | Masonry or another suitable background |
| Water brought into the building | Little: jointing compound or a thin skim | A lot, in every coat |
| Drying before decoration | Usually short | Longer, depending on thickness, conditions and the plaster used |
| Space for services and insulation | A cavity, where a frame is used | None: services are chased in or surface run |
| Line and flatness | Set out by the frame, independent of a poor wall | Follows the wall, with thickness used to correct it |
| Usual trade | Drylining fixers and tapers | Plasterers |
The guide to dot and dab vs metal-frame lining covers the two ways of drylining a masonry wall.
Where does a skim coat fit in?
A skim is a thin coat of finish plaster over plasterboard. It is still drylining, because the wall is board, but the finish is plaster rather than taped joints. Board that will be skimmed is often square-edged, and the skim is usually done by plasterers.
That makes skim a common package boundary. Check whether the skim is in your package or with a plastering subcontractor, because it changes the board you order and who returns to the wall.
Which method will a job usually call for?
- New commercial buildings. Mostly drylining: partitions and linings on metal frames, finished by tape and joint or skim.
- Housing. Either, depending on the builder's standard details, and often board with skim.
- Refurbishment of masonry walls. Either. The state of the wall, the services and any insulation upgrade decide.
- Older and listed buildings. Often specialist plasters compatible with the existing wall, which is outside a normal drylining package.
How does the choice change the programme?
Wet plaster has to dry before decoration, and drying depends on thickness, temperature and ventilation. That can hold up following trades. Drylining also needs time for jointing to dry between coats, but there is much less water to drive off.
Drylining also usually needs more visits: framing, boarding, then finishing, often with services first fix and inspections in between. Wet plastering goes on in fewer stages but needs the masonry and chases complete first. Plan your gang and visits around the sequence the main contractor's programme shows.
How do you keep the package boundary clear?
Where both trades are on a job, write down who does what:
- Who forms and finishes reveals
- Who fixes angle beads and stop beads
- Who skims board, if anyone
- Who makes good after services
- Who prepares masonry walls before bonding
Put any of these that are not yours in your exclusions. The guide to qualifications and exclusions shows how to word them.
How is each one measured and priced?
For illustration only, with assumed figures: a room 4.0 m by 5.0 m with walls 2.7 m high has 2 x (4.0 + 5.0) x 2.7 = 48.6 m² of wall. Deduct one door of 0.9 m by 2.1 m, 1.89 m², to leave 46.71 m². The activities for each method on that area:
| Activity | Dot and dab with tape and joint | Two-coat wet plaster |
|---|---|---|
| Preparation | Wall sound, dry and clean for adhesive | Wall sound, with suction controlled as the plaster needs |
| Main material | 46.71 m² of board plus waste, and adhesive | Backing coat over 46.71 m² |
| Second stage | Tape and joint every joint and internal angle | Finish coat over 46.71 m² |
| Linear items | Door reveals and any external corners | Door reveals, beads at external corners and stops |
| Waiting time | Jointing coats drying | Each coat drying, then the whole wall before decoration |
Price each activity from your own outputs and merchant prices, as the guide to building a drylining rate describes. Keep wall preparation as its own line in both.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is drylining cheaper than plastering?
It depends on the wall, the finish and the programme. Compare the full activity list for each, including preparation and waiting time, not only the material.
Is skimmed plasterboard drylining or plastering?
The wall is drylining, because it is board. The finish is plaster, usually applied by plasterers.
Why is drylining used so much on commercial jobs?
It brings little water into the building, leaves a cavity for services and insulation, and is built as tested systems for fire and acoustic performance.
Can you plaster straight onto a metal stud wall?
Not directly. A stud wall is boarded first, and the board can then be skimmed.