Recording delay and disruption evidence
Last updated 2026-11-10 · 5 min read
To support a claim for more time or loss and expense, record each delaying or disruptive event when it happens: the date, the area, what stopped or slowed the work, who caused it, the gang affected, the hours lost, and when you notified the main contractor. Records made at the time outweigh any later reconstruction.
Delay and disruption claims are usually won or lost on paperwork made at the time.
This guide gives general information. It is not legal advice. Your subcontract sets what you can claim, how and by when, so read it and take proper advice on a significant claim.
What is the difference between delay and disruption?
Delay is about time: an activity, or the whole package, finishes later than planned. It is usually linked to an extension of time and to costs that run with time, such as supervision and access equipment kept on longer.
Disruption is about productivity: the work still gets done, perhaps on time, but it takes more hours than it should because the gangs are moved around, work out of sequence or share space with other trades.
You can have one without the other, and each needs different evidence.
What does your subcontract require?
Find the clauses on extensions of time and on loss and expense, or on compensation events if the subcontract is NEC. Note:
- What events entitle you to more time or money
- What notice you must give, in what form and within what period
- Whether a late notice can cost you the entitlement
- What detail and supporting information must follow the notice
Diary the deadlines. Some subcontracts make notice within the stated period a condition of claiming at all.
What should you record when it happens?
Keep one delay and disruption record per job, filled in on the day. The example below is for illustration only.
| Date | Area | What happened | Cause and who | Gang affected | Hours lost or extra | Evidence | Notified |
|---|---|---|---|---|---|---|---|
| 6 Oct | Level 3, grid D–F | Ceiling void services incomplete, boarding stopped | M&E first fix late | 3 operatives moved to level 1 | 4 hours each in moving and setting up | Photos, site report, email to site manager | 6 Oct by email |
| 9 Oct | Level 3, core | No access, scaffold adaption not done | Main contractor's scaffold | 2 operatives standing | 3 hours each | Photos, signed standing time sheet | 9 Oct by email |
| 14 Oct | Level 2 | Boarded wall opened for late services | Revised M&E drawing | 2 operatives on rework | 7 hours each | Drawing revision, photos | 14 Oct, variation raised |
Your daily site reports should tell the same story as this record. Where the event is also a change to the work, record the change as a variation as well, as the guide to recording variations sets out. That covers the change itself; this record covers the time and productivity it cost.
What costs can a loss and expense claim include?
The heads of claim depend on your subcontract and the facts, but commonly include:
- Prolongation. Time-related costs for the extra period, such as supervision, access equipment, welfare or vehicles.
- Disruption. Extra labour hours caused by working inefficiently.
- Standing time. Operatives on site who could not work.
- Remobilisation. Leaving an area and coming back to it.
Each cost needs a record behind it: timesheets, hire invoices and payroll. A claim for head office overheads or lost profit is usually harder to prove and generally needs more detailed evidence.
How do you show lost productivity?
One accepted approach compares your output in a disrupted area with your output on comparable work that was not disrupted, sometimes called a measured mile. It only works if you already record outputs by area and activity, as the guide to drylining productivity describes.
For illustration only, with assumed figures: on level 1, undisrupted, your gangs boarded 10 m² per operative per day. On level 3, where they were repeatedly moved, they boarded 1,200 m² at 8 m² per operative per day, which took 150 operative days. At the level 1 output it would have taken 120. The 30 lost operative days, at an assumed £200 per operative day, come to £6,000.
The comparison must be fair. The two areas should be similar work, and any slow-down that was your own responsibility, such as a short gang or a supply problem of your own, has to come out of the figure.
How do you keep the claim alive?
Send the notice when the event happens, not when the job ends. Follow it with the details your subcontract asks for, and update the figures monthly while the effect continues. Show the claim as a separate line on each payment application, so it stays in view until it is agreed or decided.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can I claim loss and expense without an extension of time?
Sometimes. Disruption can cost money without delaying completion. Whether you can recover it depends on the events your subcontract covers.
How soon should I notify a delay?
As soon as you are aware of it, and within any period your subcontract sets. A late notice can weaken or lose the claim.
Are photos enough evidence?
Photos help, but they work best with a dated record of the event, the gang affected and the hours lost, and a copy of the notice you sent.