Contingency and risk in a subcontract price

Last updated 2026-11-10 · 5 min read

Short answer

A risk allowance should come from a list of named risks, not a blanket percentage. For each one, estimate what it would cost and how likely it is, then decide whether to price it, qualify it or exclude it. Price the risks you can control and that the main contractor expects you to carry. Qualify the ones that depend on others.

Every subcontract price carries some risk. The question is whether you have decided which risks you are carrying, or whether they are sitting unpriced in a rate that looks competitive.

Why is a flat contingency percentage a weak answer?

Adding a fixed percentage to every tender treats a simple ground-floor fit-out and a congested refurbishment in an occupied building the same way. It is too much on one and too little on the other. It also tells you nothing at the end of the job: you cannot see which risk used the money, or whether the allowance was right.

A short risk list, priced item by item, gives you a figure you can explain, defend in a tender review and check against the outcome.

Which risks does a drylining package usually carry?

Start with the documents and the site, not a standard list. Common sources are:

  • Design not complete: heights, head details or partition types still to be confirmed
  • Sequence and access: other trades in the way, late services, restricted working areas
  • Return visits: boarding left open for services, then closed later
  • Productivity: tight risers, high walls, many short runs, occupied areas
  • Material prices: rises between tender and call-off, if your price is fixed
  • Programme: a compressed period needing more labour or overtime

How do you put a value on each risk?

For each risk, estimate the cost if it happens and the chance that it will. Multiply them to get an expected cost. That figure is a guide, not a promise: if the risk happens, you carry the whole cost, not the expected value.

Then make a decision for each line:

  • Price it when the risk is yours to manage and the main contractor will expect it to be in your price
  • Qualify it when it depends on information or actions you do not control, and state your assumption
  • Exclude it when the work is genuinely outside your package

What does a risk register for one tender look like?

For illustration only, with assumed figures. A drylining package on a six-storey office refurbishment.

RiskCost if it happensAssumed chanceExpected costDecisionIn price
Two extra return visits to close up after services£2,40050%£1,200Price£1,200
Lower output in congested riser areas£1,80040%£720Price£720
Slab heights on level 4 greater than drawn£3,00030%£900Qualify against section drawing£0
Board price rise before call-off£4,00025%£1,000Qualify with a price validity period£0
Total£3,820£1,920

The priced allowance is £1,920. The other two risks are covered by written assumptions, so if they happen they become a variation or a re-price rather than a loss. Each qualification needs specific wording, as the guide to qualifications and exclusions explains. For the price validity point, see fixed price vs fluctuations.

Where should the allowance sit in the price?

Many subcontractors keep the priced allowance inside the rates or the package preliminaries rather than showing a line called "contingency". A named contingency line can be read as something to negotiate away or to adjust like a provisional sum, which it is not.

Inside your own build-up, keep it as a separate line so you know what it is and can track it. If the main contractor asks to see your risk allowance, decide in advance how much detail you are prepared to share.

How do you know if the allowance was right?

Keep the risk register with the job file. During the job, note which risks happened and what they cost. At the end, compare:

  • The allowance you priced
  • The cost of the risks that happened
  • Any risks you did not list at all

Over several jobs, that shows whether your allowances are too heavy, too light, or missing whole categories. The guide to tracking margin on a live interiors job covers watching the job cost while the work is still going on.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

What percentage contingency should a subcontractor add?

There is no standard figure. Build the allowance from the risks on the job in front of you, item by item, rather than a fixed percentage.

Is contingency the same as a provisional sum?

No. A provisional sum is set by the client for work not yet defined and is adjusted to the actual cost. Your risk allowance is part of your own price.

Should I tell the main contractor about my risk allowance?

That is a commercial decision. Many keep it within rates or preliminaries. Qualifications, by contrast, must be stated clearly in the tender.

What if a priced risk never happens?

The allowance stays in your margin. Across many jobs, some risks happen and some do not, which is why the expected cost is a guide.