Scheduling material deliveries on site
Last updated 2026-11-10 · 6 min read
To schedule drylining deliveries, work back from the date each area starts on the programme: subtract the merchant's lead time, the site's booking notice and a buffer to get the latest order date. Then book a delivery slot under the site's logistics rules, name who will receive it, and keep a two- to three-week look-ahead that you update every week.
Material that arrives too early gets moved, damaged or stolen. Material that arrives too late leaves a gang waiting. A delivery schedule turns the programme into dates for ordering, booking and receiving, so each drop lands when the area is ready for it.
What does the site need from you before a delivery?
Most main contractors run a logistics plan. Before the first order, find out:
- Delivery hours, and whether out-of-hours deliveries are allowed
- How much notice is needed to book a slot, and how to book it
- Vehicle limits: size, weight, and the route to the gate
- Who unloads, with what, and whether a crane, forklift or hoist must be booked
- Where material can be stored, and any limits on loads on the floors
- Whether deliveries must be shared or coordinated with other trades
Put the answers on the first page of your schedule and send them to every merchant on the job, so drivers arrive knowing the rules.
How do you work out when to order?
Start from the date work begins in each area and count back. For each delivery, you need:
- Date needed on site. Usually a day or two before the gang starts, not weeks before.
- Site booking notice. The notice the main contractor needs to book the slot.
- Merchant lead time. Confirmed with the merchant for the specific products, especially less common boards or long lengths.
- Buffer. A margin for a missed slot or a short delivery.
The example below is for illustration only, with assumed lead times.
| Area | Gang starts | Needed on site | Site booking notice | Merchant lead time | Buffer | Latest order date |
|---|---|---|---|---|---|---|
| Level 2 boarding | Mon, week 6 | Thu, week 5 | 2 working days | 3 working days | 2 working days | Thu, week 4 |
| Level 3 framing | Mon, week 7 | Thu, week 6 | 2 working days | 3 working days | 2 working days | Thu, week 5 |
| Level 3 acoustic board | Mon, week 8 | Thu, week 7 | 2 working days | 10 working days | 3 working days | Mon, week 5 |
Counting back from Thursday of week 5 for level 2: 3 days of lead time takes you to Monday of week 5, and 2 days of buffer to Thursday of week 4. The booking notice falls inside the lead time, so book the slot as soon as the merchant confirms the delivery date. The acoustic board shows why long-lead items need their own line: it has to be ordered before level 2 has even been delivered.
What should a delivery schedule show?
Keep one schedule per job, alongside your call-off register, which tracks quantities against the take-off. The schedule tracks dates and logistics. The example below is for illustration only.
| Delivery ref | Area | Items | Merchant | Order date | Booked slot | Offload | Store at | Receiver | Status |
|---|---|---|---|---|---|---|---|---|---|
| D-07 | Level 2 | Boards, jointing materials | Merchant A | Thu, week 4 | Thu, week 5, 08:00 | Forklift, then hoist | Level 2 core | Site manager | Booked |
| D-08 | Level 3 | Studs, track, insulation | Merchant A | Thu, week 5 | Thu, week 6, 07:30 | Forklift, then hoist | Level 3 east | Gang leader | Ordered |
| D-09 | Level 3 | Acoustic board | Merchant B | Mon, week 5 | Thu, week 7, 08:00 | Forklift, then hoist | Level 3 core | Site manager | Ordered, lead time confirmed |
Each delivery should link to a purchase order or call-off, so the delivery note and invoice can be traced back. The guide to drylining purchase orders shows what to put on the order, including the delivery details.
How far ahead should you look?
Two to three weeks is usually enough for standard items, with longer for anything with a long lead time. Review the look-ahead each week against the latest programme, and move delivery dates as soon as an area slips. A delivery that arrives on the original date to a floor that is not ready has to be stored somewhere, and often moved twice.
What happens when the delivery arrives?
The named receiver should be at the gate at the booked time, check the load against the order before signing, and record any shortage or damage on the delivery note. Material should go straight to the agreed storage point, protected from weather and other trades. The guide to drylining call-offs covers how to keep what is ordered in line with what was priced.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
How early should drylining materials be delivered?
Usually a day or two before the gang starts in that area. Earlier deliveries increase the risk of damage and double handling.
Who books the delivery slot?
Usually you, through the main contractor's booking system. Check how the site handles bookings before the first order.
What if the merchant cannot meet the date?
Find out at order, not on the day. Move the gang to another area or source the item elsewhere, and tell the site manager.
Should the delivery schedule follow the programme?
Yes. Update it every week against the latest programme, and change delivery dates as soon as an area slips.