Purchase orders for drylining subcontractors: what to include
Last updated 2026-11-08 · 6 min read
A drylining purchase order should name the job and delivery address, the exact product for each line, the quantity and unit, the agreed price, and the delivery date and access rules. Give it a unique number, and ask the merchant to quote that number on the delivery note and invoice, so each can be checked against the order.
A purchase order is your record of what you agreed to buy, at what price. Without one, the delivery note and the invoice are the only records, and both are written by the merchant. With one, every later check has something to compare against.
Why do drylining jobs need purchase orders?
Drylining materials arrive in many drops over a long programme, from more than one merchant, often at prices agreed for that job. That makes it easy to:
- Accept a delivery of the wrong product or the wrong quantity.
- Pay a list price instead of the price agreed for the job.
- Lose track of what has been ordered against the bill of quantities.
- Book a cost to the wrong job.
A purchase order for each order, or each call-off against a larger order, closes those gaps. The guide to drylining call-offs covers how call-offs and orders fit together.
What should a purchase order include?
The lines a merchant needs to deliver the right thing, and you need to check it:
| Section | What to include |
|---|---|
| Order number | A unique number, quoted on the delivery note and the invoice |
| Job | Job name or number, so the cost lands on the right job |
| Delivery address | Site address, with the gate or entrance to use |
| Contact | The site contact and their phone number |
| Products | Exact product description and the merchant's code for each line |
| Quantity and unit | Quantity in the unit the merchant sells in, such as board, length or pack |
| Price | The price agreed for this job, per unit, with any quote reference |
| Delivery | Date, time window, offload method and any vehicle limits |
| Terms | Which quote or account terms the order is placed under |
Write the product exactly as the specification and quote describe it. A similar board from a different range may not meet the fire or acoustic rating of the system.
How do you get the units right?
Order in the unit the merchant sells in, and check it matches the unit on the quote. A line ordered as packs and priced per board, or the other way round, is one of the most common reasons an invoice does not match.
Where your take-off is in square metres or linear metres, turn it into boards, lengths or packs before you raise the order, and keep the working with the order.
What delivery details should go on the order?
Delivery problems cost time on site. State:
- The date and time window, and whether a booked slot is needed.
- How the load will be taken off: crane offload, tail lift or by hand.
- Any limits on vehicle size, weight or route to the gate.
- Where materials go: to a floor, a storage area or a loading bay.
- Who on site will receive and sign for the delivery.
What do you check when the goods arrive?
Check the delivery against the order, not against the delivery note alone:
- Each product matches the line on the order.
- The quantity received matches, or the shortfall is written on the note.
- Damaged items are noted before the note is signed.
Record what was received. That record, often called a goods received note, is what the invoice is checked against later.
How do you check the invoice against the order?
Compare three documents line by line: the purchase order, the record of what was received and the invoice. Query any line where the product, quantity or price does not match. The guide to checking supplier invoices covers the steps in detail.
For illustration only, with assumed figures: an order is for 180 boards at £9.40 each, which is £1,692.00, and 400 studs at £3.15 each, which is £1,260.00, plus a £45.00 delivery charge, so £2,997.00 in total. The invoice comes in at £3,087.00. Checked line by line, the boards are charged at £9.90 each, which is 180 x £0.50 = £90.00 more than the agreed price, so that line is queried.
How do you keep track of orders on a long job?
Keep a register of every order against the job: order number, merchant, lines, value, delivery date and status. It shows what is still to come, and it stops the same items being ordered twice. The guide to keeping a call-off register has a table you can copy.
FixMargin is software for UK drylining and interiors subcontractors. Purchase orders, goods received notes and invoice checks are on the Starter plan and above, and each invoice line is checked by a person in your team against what was ordered and received. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Does every delivery need its own purchase order?
Not always. You can raise one order for the job and call off against it, as long as each call-off is recorded against that order.
Should the price be on the purchase order?
Yes. Put the price agreed for this job on every line, with the quote reference, so the invoice can be checked against it.
What is a goods received note?
A record of what actually arrived on site, line by line. It sits between the purchase order and the invoice when you check what you owe.
What should I do if an invoice does not match the order?
Query the lines that do not match, in writing, and hold payment of those lines until the merchant answers. Pay the lines that do match on time.