Labour-only vs supply-and-fix drylining

Last updated 2026-11-10 · 6 min read

Short answer

On a labour-only drylining package, the main contractor buys the boards, metal and sundries, and you supply the people to fix them. On supply-and-fix, you buy and fix everything. Supply-and-fix gives a bigger subcontract value and a profit on materials, but you also carry waste, price rises, losses and the cash tied up in stock.

Both are common in UK interiors work, and many subcontractors run both. The choice changes your risk, paperwork and cash far more than the work your gangs do.

What does each arrangement cover?

In a labour-only package, your price covers the labour to install the work, plus whatever the subcontract adds: supervision, setting out, small tools, and sometimes fixings. The main contractor orders the materials, takes the deliveries and owns the stock.

In a supply-and-fix package, your price covers the installed work: materials, waste, delivery, distribution, labour and your margin. You choose the merchant, place the orders and pay the invoices.

Read labour-only enquiries carefully. Some still expect you to provide screws, tape, sealant or beads. If it is not stated, ask, and put the answer in your offer.

Who carries which risk?

ItemLabour-onlySupply-and-fix
Ordering and call-offsMain contractorYou
Material prices rising after the tenderMain contractorYou, unless the subcontract allows fluctuations
Waste and offcutsMain contractor, though they may question excessive useYou
Short or damaged deliveriesMain contractorYou, with the merchant
Theft and damage to stored stockOften the main contractor, unless your gang causes it; check the subcontractOften you, until the work is handed over; check the subcontract
Delays caused by late materialsMain contractor, and a possible claim for youYou
Cash paid out before you are paidLabour and supervisionLabour, supervision and materials

On labour-only work, a shortage of materials is the main contractor's problem, but it stops your gang. Record every hour lost waiting, because that is the evidence for any claim.

How do CIS and VAT differ between the two?

Under the Construction Industry Scheme, the contractor's deduction is taken from the labour part of each payment, after VAT and after the cost of materials you bought for the work. On a labour-only package, nearly the whole payment is labour, so the deduction applies to nearly all of it. On supply-and-fix, the materials you bought are taken out first, so show them clearly on every application. The guide to CIS deductions works through the figures.

The VAT domestic reverse charge can apply to both. It turns on VAT registration, CIS reporting and whether the customer has told you in writing that it is an end user or intermediary, as the reverse charge guide explains. These are general rules, not tax advice. Check HMRC's guidance on gov.uk and ask your accountant how they apply to you.

What does the difference look like on one job?

For illustration only, with assumed figures. A partition package needs £30,000 of labour, including supervision, and £27,000 of materials, waste and delivery.

LineLabour-onlySupply-and-fix
Subcontract value£36,000£66,000
Materials, waste and delivery£0£27,000
Labour and supervision£30,000£30,000
Gross profit£6,000£9,000
Gross margin16.7%13.6%
Materials paid before you are paidNoneMost of the £27,000

Supply-and-fix earns more in pounds here, but at a lower margin, with more cash out and more ways to lose money. If waste runs 3% higher than allowed on the materials, that costs about £810, which is 9% of the profit. On labour-only, the same overrun is not your cost, but your own labour still has to come in on budget. The guide to plasterboard waste allowance shows how to set that allowance.

Which one suits your business?

Labour-only tends to suit a business with strong gangs and supervisors, little working capital, or a main contractor who buys materials on better terms than you can. Your margin then rests on labour productivity and on recording time lost to others.

Supply-and-fix tends to suit a business with merchant accounts, someone to manage orders and deliveries, and the cash to carry materials between valuations. It rewards good buying and tight control of waste.

Either way, build your labour cost the same way, as the guide to setting your drylining labour rate explains.

What about the gangs you engage yourself?

Many drylining subcontractors take on labour-only gangs of their own. If you do, you act as a contractor under CIS: register, verify each subcontractor with HMRC before paying them, make the deductions and file the monthly returns. Check each worker's employment status against HMRC's employment status guidance as well. This page cannot tell you how those rules apply to a particular gang.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Is labour-only drylining less risky?

It carries less material risk, but your margin then rests almost entirely on labour. Lost time, slow outputs and return visits hit it directly.

Does a labour-only package include fixings?

Only if the subcontract says so. Some do include screws, tape and sealant, so ask and state the answer in your offer.

Is CIS deducted from materials on supply-and-fix?

No. The deduction is worked out after VAT and the cost of materials you bought for the work, as HMRC defines materials.

Can one job be part labour-only and part supply-and-fix?

Yes. Some packages split it, for example free-issue boards with your own metal. Set out who supplies each item in a table in your offer.