Goods received notes: checking deliveries

Last updated 2026-11-10 · 6 min read

Short answer

A goods received note (GRN) is your own record of what actually arrived on site, checked line by line against the purchase order. It records the quantity accepted, any shortage, damage, substitution or over-delivery, who checked it and when. It is the document you later check the invoice against, and the point at which the cost belongs on the job.

The merchant's delivery note says what the merchant sent. The GRN says what you received and accepted. On most drylining jobs they agree. When they do not, the GRN is how you prove it.

How is a GRN different from a delivery note?

DocumentWritten byWhat it shows
Purchase orderYouWhat you asked for, at what price
Delivery noteThe merchantWhat the merchant says it sent
Goods received noteYouWhat arrived, what you accepted, and what was wrong
InvoiceThe merchantWhat the merchant says you owe

Signing the delivery note confirms receipt. The GRN records the check behind that signature. Many merchants' terms set a short period for reporting shortages or damage, so read your account terms and record problems on the delivery note before you sign it as well.

What should a GRN record?

For each line on the purchase order:

  • Quantity ordered
  • Quantity on the delivery note
  • Quantity counted on arrival
  • Quantity damaged or rejected
  • Quantity accepted
  • Any substitute product, with its description, and whether it was accepted
  • Notes, such as "short, back order promised"

And for the delivery as a whole: the order and delivery note numbers, date and time, the person who checked it, and photos of anything damaged.

What does a completed GRN look like?

The example below is for illustration only, with assumed figures and prices taken from the purchase order.

PO lineOrderedDelivery noteCountedDamagedAcceptedPriceAccepted value
Standard board1801801723169£9.40£1,588.60
Studs4004004000400£3.15£1,260.00
Delivery charge11——1£45.00£45.00
Total£2,893.60

The order was for £2,997.00. Eight boards were short and three were broken, so 11 boards, worth 11 x £9.40 = £103.40, were not accepted. The difference, £2,997.00 - £2,893.60 = £103.40, is what the merchant needs to redeliver or credit. Note it on the delivery note at the time, photograph the broken boards, and tell the merchant in writing the same day.

How do you handle the awkward cases?

  • Part delivery. Accept what came and leave the rest of the order open. The next delivery gets its own GRN.
  • Substitution. Do not accept a different product without checking it. A board from another range may not meet the fire or acoustic rating the system needs. If it is accepted, record what it is and who agreed it.
  • Over-delivery. Record the extra quantity and agree with the merchant whether it stays, at what price, or is collected.
  • Unchecked delivery. If a load cannot be checked when it arrives, write that on the delivery note and check it as soon as possible. Do not assume this protects you if the account terms say otherwise.

How does the GRN feed the job cost?

The GRN is the point at which material becomes a cost to the job, valued at the order price. Book it once, against the right job and cost code.

When the invoice arrives, compare it with the GRN rather than adding it as a new cost. In the example, an invoice for the full £2,997.00 would show £103.40 more than was accepted, so that difference goes on your invoice query log until it is credited or redelivered. The cost already recognised from the GRN stays as it is. If the invoice price differs from the order price, adjust the cost by the difference only. The guide to checking supplier invoices covers the line-by-line check.

At month end, count goods received but not yet invoiced at their GRN value, once. Do not add a further accrual for the same goods, because they are already in the cost.

Who should complete the GRN, and when?

The person who receives the delivery, at the time it arrives, using a copy of the purchase order. Site knows what came off the lorry. The office knows the prices. The GRN joins the two, which is why each order needs a number the merchant quotes on the delivery note, as the guide to drylining purchase orders describes.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. Purchase orders, goods received notes and invoice checks are on the Starter plan and above, and each invoice line is checked by a person in your team against what was ordered and received. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Is a signed delivery note the same as a GRN?

No. The delivery note is the merchant's document. The GRN is your record of what you checked and accepted.

Should I refuse a damaged delivery?

Refuse or record the damaged items, depending on your account terms, and note it on the delivery note before you sign. Photograph the damage.

Who keeps the GRN?

Keep it with the purchase order, where whoever checks the invoices can find it.

Do small deliveries need a GRN?

A short GRN is still worth it. Small deliveries are where shortages most often go unnoticed.